Project Phases

Al Amerah Infrastructure Package 02 Β· Choose a phase to view its dashboard

Loading…
← Project Overview

Choose a project phase

Each phase has its own dedicated dashboard. Percentages are pulled live from the BOQ Google Sheet on each page load.

🎯
Milestones
Contractual milestones & authority approvals
0%awaiting data
Awaiting data→
🚧
General / Mobilization
Preliminaries, site setup, NOCs, OSH plans
0%β€” / β€”
Awaiting data→
πŸ“
Design
Drawing register, IFCs, design approvals
0%β€” / β€”
Awaiting data→
βš™οΈ
Engineering
Shop drawings, submittals, method statements
0%awaiting data
Awaiting data→
πŸ“¦
Procurement
POs, deliveries, long-lead items
0%awaiting data
Awaiting data→
πŸ—οΈ
Construction
Per-discipline progress, KPI S-curves, daily reports
0%β€” / β€”
Live→
πŸ§ͺ
Testing & Commissioning
IRs, pressure tests, CCTV reports
0%awaiting data
Awaiting data→
🏁
Handover & Closeout
Snag list, as-builts, DLP, final account
0%awaiting data
Awaiting data→
Al Amerah Infrastructure Package 02 Β· Noor Al Sahara Contracting Β· Planning Department
Developed by Eyad M. Refai