Total Contract Value
AED 880,000,000
Eight Hundred and Eighty Million UAE Dirhams
Contract Timeline
Commencement Date
16-FEB-2026
Day 1 of 967
Days Elapsed / Remaining
85 / 881
8.8% of contract time elapsed
Completion Date
09-OCT-2028
967 Calendar Days
16 Feb 2026
Today
09 Oct 2028
Time elapsed
Physical progress (P6)
Today
Project Parties
Client
M/s Abu Dhabi Housing Authority
Employer
M/s ALDAR Projects L.L.C — O.P.C
Project Management Consultant
M/s Ellisdon Construction Inc.
Design & Supervision Consultant
M/s AECOM
Main Contractor
M/s Noor Al Sahara Gen Contracting — Sole Proprietorship LLC
Contract Type
Design & Build — Lump Sum Fixed Price
Scope of Work
Sewerage Network
62,000 LM Pipes · 2,905 Manholes · 1,095 House Connections
Storm Water Drainage
Design & Build · All sectors
Potable Water Network
Design & Build · Distribution mains
Irrigation Network
Treated water irrigation · All plots
Roads & Paving
54 KM roads · 6,665 parking spaces
Electrical Infrastructure
82 × 11KV Substations · Street lighting
Telecommunications
Ducting & infrastructure · All plots
Site Location · Al Amerah, Al Ain