Al Amerah Infrastructure — Site Progress Map

Noor Al Sahara Contracting · Planning Department · Package 02

Baked-in data
Data date03 May 2026

Select a Discipline

Live progress map per discipline — showing completed work, team information and daily resources. Click any active discipline to open its map.

● Active
🔴
Sewer Water Network
GRP & UPVC sewer pipes, manholes, house connections, CCTV testing
Overall weighted progress 7.73%
Construction stages
Exc
97%
Lay
0%
BFill
0%
Test
0%
CCTV
0%
Pipe excavation
3,186 LM
Overall %
7.73%
Manholes exc.
60 Nos
Last update
03 May 2026
Open Progress Map  →
Not started
🔵
Storm Water Drainage Network
Storm drainage pipes, catchpits and outfall structures
Overall weighted progress0%
Qty done
Overall %
0%
Activities
Last update
Not started yet  —
Not started
💧
Potable Water Network
Water mains, service connections and isolation valves
Overall weighted progress0%
Qty done
Overall %
0%
Activities
Last update
Not started yet  —
Not started
🌿
Irrigation Water Network
Irrigation network, distribution pipes and control valves
Overall weighted progress0%
Qty done
Overall %
0%
Activities
Last update
Not started yet  —
Not started
📡
Telecom Network
Telecom ducts, chambers and fibre optic cable routes
Overall weighted progress0%
Qty done
Overall %
0%
Activities
Last update
Not started yet  —
Not started
MCC Network
Motor control centre network, cable routes and connections
Overall weighted progress0%
Qty done
Overall %
0%
Activities
Last update
Not started yet  —
Not started
🔌
Electrical Network
LV/HV electrical ducts, cables and distribution points
Overall weighted progress0%
Qty done
Overall %
0%
Activities
Last update
Not started yet  —
Not started
💡
Street Lighting Network
Lighting ducts, pole foundations, poles and luminaires
Overall weighted progress0%
Qty done
Overall %
0%
Activities
Last update
Not started yet  —
Not started
🛣️
Road Works
Subbase, base course, asphalt paving and road reinstatement
Overall weighted progress0%
Qty done
— m²
Overall %
0%
Activities
Last update
Not started yet  —
Not started
🏗️
Distribution Substation
Cluster No. 6 — 13 substations civil and electrical works
Overall weighted progress0%
Qty done
Overall %
0%
Substations
0 / 13
Last update
Not started yet  —
Al Amerah Infrastructure Package 02 · Progress Map · Noor Al Sahara Contracting