ALDAR · AIP2 Package 02
Al Amerah Infrastructure
Progress Dashboard
Client: ALDAR Properties

Al Amerah Infrastructure — Site Progress Map

Noor Al Sahara Contracting · Planning Department · Package 02

Baked-in data
Data date09 May 2026
← Phases

Select a Discipline

Live progress map per discipline — showing completed work, team information and daily resources. Click any active discipline to open its map.

● Active
🔴
Sewer Water Network
GRP & UPVC sewer pipes, manholes, house connections, CCTV testing
Physical Progress 0.86%
Construction stages
Exc
2%
Lay
0%
BFill
0%
Test
0%
CCTV
0%
Pipe excavation
2,211 LM
Overall %
0.86%
Manholes exc.
171 Nos
Last update
03 May 2026
View S-Curve KPI  📈
Open Progress Map  
Not started
🔵
Storm Water Drainage Network
Storm drainage pipes, catchpits and outfall structures
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Not started
💧
Potable Water Network
Water mains, service connections and isolation valves
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Not started
🌿
Irrigation Water Network
Irrigation network, distribution pipes and control valves
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Not started
📡
Telecom Network
Telecom ducts, chambers and fibre optic cable routes
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Not started
MCC Network
Motor control centre network, cable routes and connections
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Not started
🔌
Electrical Network
LV/HV electrical ducts, cables and distribution points
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Not started
💡
Street Lighting Network
Lighting ducts, pole foundations, poles and luminaires
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Not started
🛣️
Road Works
Subbase, base course, asphalt paving and road reinstatement
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Not started
🏗️
Distribution Substation
Cluster No. 6 — 13 substations civil and electrical works
Physical Progress0%
Budgeted LU
Overall %
0%
Actual LU
Last update
View S-Curve KPI  📈
Not started yet  —
Al Amerah Infrastructure Package 02 · Progress Map · Noor Al Sahara Contracting